Maryland Portal Home
 
Click here for Accessible Site Navigation
Home
Business Center
Projects & Studies
Commuter & Travel
Safety Programs
Environment & Community
Info Center

Contractors Information Center

Welcome to the MDOT State Highway Administration (MDOT SHA) Contractors Information Center (CIC) Web Site. MDOT SHA advertises and awards construction and maintenance contracts for the state highway system. This web site is designed to provide contractors with information on highway construction projects, it is not to be used as a substitute for the current bidding process. If you would like to find out more about the bidding process see the How to Bid section of the site. If you require additional information related to advertised contracts, bids or proposals please contact us at cic@sha.state.md.usPlease call 410-545-8840 or email us at MdotSHABidX@sha.state.md.us for questions regarding MDOT’s implementation of the Bid Express system.  If you require assistance related to other topics, please consult Contact Us for the appropriate contact email addresses.

 

CONTRACTOR NEWS

CONTRACTORS....Update your company's vendor information for MDOT SHA'S Engineer's Estimate and Construction Contract System AASHTO'S TRNS*PORT!

 

IMPORTANT NEWS!

E-Bid Update (December 08, 2017): There are three situations when a bidder MUST re-attach ALL the attachment files when resubmitting a bid:

  • MDOT SHA postpones a proposal to a different letting date;
  • MDOT SHA postpones a proposal and then re-uploads the proposal to the same letting where it was originally uploaded; or
  • MDOT SHA withdraws a proposal and then reposts that proposal to the same letting where it was originally uploaded.
Re-attaching attachments means navigating to EVERY attachment location in the ".ebsx file" and re-selecting the attachment using the 'Browse' button, prior to re-submission.


E-Bid Update (August 29, 2017): For all highway improvement and highway maintenance projects advertised henceforth the Maryland Department of Transportation's State Highway Administration will accept only electronic bids. The bid needs to be submitted at https://www.bidx.com/maryland/main. Paper bids will not be accepted. Instructions on electronic bidding are available here.



Standard Specification for Construction and Materials

The 2017 Edition of the Standard Specification for Construction and Materials is now available. This edition is available exclusively in an online MediaWiki format, a physical copy is not available for sale. The Standard Specification and Supplemental documents may be found on the MDOT SHA web site under the Business Standards - Business Standards and Specifications section, or at the following link:

Standard and Supplemental Specifications For Construction and Materials

Please direct any questions regarding the standard specification to specifications@sha.state.md.us.


eMaryland Marketplace

Since August 4, 2015, MDOT SHA has been posting project links for eMaryland Marketplace (eMM) on the Contractors Information Center (CIC) project page. This option makes it easier for contractors to find the project information on eMM. As of March 15, 2016 MDOT SHA will not post the actual pre-bid documents for the advertisements, addenda and project quantities on the CIC. These documents along with the “qty.z” file will be found on eMM for each project link provided. The last addendum with revised quantities will have the all-inclusive list of items in the contract, if applicable.

All post-bid documents such as bid results, bid tabulations and final Plan purchasers’ list will continue to be posted on the CIC.

MDOT State Highway Administration has a new process for administering Construction Documents through eMaryland Marketplace (eMM).  Bidders must register, login, and verify amendments in order to receive a Contract Award. Registration is free and there is no cost for the Contract Documents.

Refer to the "Notice to the Contractor" in "Invitations for Bid Book" for additional instructions.

With the implementation of eMaryland Marketplace processes, please note that MDOT SHA’s Cashier’s Office at 211 East Madison Street will be CLOSED effective August 28, 2015. Bidders will no longer be required to purchase Contract Documents. All Contract Documents will be available on eMaryland Marketplace and can be downloaded at no cost.

The 2008 Standard Specification for Construction and Materials book, which was previously available for purchase at the Cashier’s Office, is no longer being sold. You may obtain an electronic version from the Standard Specification for Construction and Materials site.   


Click to go to eMARYLAND MARKETPLACE  

Click to view eMM - MDOT SHA Contracts and Bids' Plan Holders List (log in required)

 

For additional information on Contract Number (MO3515172) Click here

Contractor's Inquiry Responses

Contract No.MO3515172

Inq. 178Post Date:   11/5/2015Inquiry Date:   10/29/2015
 Q. Retaining Wall sheet S5-4, Wall Section C indicates that it is a lower elevation than the BB to the left, but they both have the same number. What is the correct elevation for Section CC?
 A. The elevation is lower for Section C at Elev 334.17. Addendum No 1 answers this question.
Inq. 177Post Date:   11/5/2015Inquiry Date:   10/29/2015
 Q. There is Type Ill fencing for S13, but no Bid Item. Will a bid item be added? Also, the post layout exceeds the drawing detail for fence location at the Station 406.. End. Will this drawing be modified?
 A. A bid item was added for this fence. Addendum No. 1 will answer this question. Structure S-13 runs from Sta 247+45.63 to Sta 252+00. It does not extend to Sta 406+.
Inq. 176Post Date:   11/5/2015Inquiry Date:   10/29/2015
 Q. There are Fencing Bid Items Type Ill for S4, SS, and S12, but the plans do not indicate any of this type of fencing. Will the drawings be changed to add fencing?
 A. The typical sections for Structure S5 show and label the fence type. Addendum No. 2 will include the label on the Elevation View.
Inq. 175Post Date:   11/5/2015Inquiry Date:   10/28/2015
 Q. Please confirm that the 13 feet undercut and backfill for structure S6 is covered under bid Item 4015
 A. The overexcavation is covered with Item 4015, and the quantity has been reduced significantly for Addendum 2. The revised extent of overexcavation, along with how this work is to be paid, is shown in the Addendum 2 plans. The backfill for the overexcavated zone will be covered in Addendum 2, under a separate item (Graded Aggregate Base, S6).
Inq. 174Post Date:   11/5/2015Inquiry Date:   10/28/2015
 Q. Bid Items 4054 and 4067 for structure S6 seem to be for the retaining walls/ wingwalls for the culvert. Please confirm.
 A. Item 4054 will be removed. Item 4067 will remain, and includes the concrete traffic barrier attached to the downstream headwall and wing walls of S6.
Inq. 173Post Date:   11/5/2015Inquiry Date:   10/28/2015
 Q. There are multiple pay items for structure S6, please clarify the scope covered under each: a. Item 114004: S6 Box Culvert 12'x6'; b. Item #4053: Footing Concrete S6;c. Item #4071: Single Reinforced Box Culvert S6
 A. Item 4004 and Item 4053 will be removed. Item 4071 will remain. The scope of work covered under Item 4071 is provided in the contract documents.
Inq. 172Post Date:   11/5/2015Inquiry Date:   10/26/2015
 Q. S6 and S11 both have notes about undercut excavation and backfill under the culverts. Please provide limits of payment as well as how it is to be paid.
 A. The excavation and back fill is to be paid per cubic yard. Addendum No. 1 for S11 and Addendum No. 2 for S6 will answer this question.
Inq. 171Post Date:   11/5/2015Inquiry Date:   10/26/2015
 Q. Sheets S12-30, pier 2 elevation view shows proposed ground approximately 4.5' below existing ground. This is not reflected on the cross section sheet 120 of 153, which only shows existing ground. Please clarify the proposed ground elevation in this area.
 A. This information will be provided in the near future.
Inq. 170Post Date:   11/5/2015Inquiry Date:   10/26/2015
 Q. Please refer to Item 4054 Substructure Concrete for Bridge S6. This structure is a box culvert and not a bridge, please confirm if this item is for wingwall concrete for culvert or if this item is not needed.
 A. Item 4054 will be removed in Addendum No. 2. The wingwall concrete is incidental to the box culvert pay item.
Inq. 169Post Date:   11/5/2015Inquiry Date:   10/26/2015
 Q. Is all CIP concrete for the S11 Box Culvert to be paid under item 4070 Single Reinforced Concrete Box Culvert S11?
 A. All cast in place and precast concrete from the existing pipe to the wing walls are incidental to the bid item.
Inq. 168Post Date:   11/5/2015Inquiry Date:   10/23/2015
 Q. There is no pay item for the 6" Subdrain Pipe for the stormwater management filtration facilities. Can a pay item be added for this item of work?
 A. This item is paid for under Item No. 3084 “6 Inch Perforated Circular Pipe Longitudinal Underdrain” and Item No. 3085 “6 Inch Perforated Circular Pipe Underdrain”.
Inq. 167Post Date:   11/5/2015Inquiry Date:   10/22/2015
 Q. Please check the quantity for Item 7010- Temporary Seed- 227,857 LB. Should the unit of measure be SY? Please advise
 A. Item 7010 should be measured as SY, CCS No. should be705405 and not 705400.
Inq. 166Post Date:   11/5/2015Inquiry Date:   10/22/2015
 Q. Please provide an Item for the Type III fence for retaining wall S13.
 A. Addendum No. 1 will answer this question.
Inq. 165Post Date:   11/5/2015Inquiry Date:   10/22/2015
 Q. Sheet S13-2: the fence post spacing dimensions do not match the drawing and required end transition. Please clarify.
 A. This will be revised in Addendum No. 2.
Inq. 164Post Date:   11/5/2015Inquiry Date:   10/22/2015
 Q. On sheet S6-4 Note 3 states “The existing soil below the proposed box culvert and wing walls shall be over excavated by 13'-0" and backfilled with suitable material." Is it really the Intent to over excavate 13'? Is this be paid under the Lump Sum S6 culvert Item? What type of material is to be used for suitable material for backfill?
 A. The amount of over excavation has been reduced significantly. The revised quantity of over excavation, along with how this work is to be paid, is shown in the Addendum No. 2. The excavation will be paid for under Item 4015 (Class 3 Excavation, S6) which is included in Addendum No. 1 and the backfill will be Graded Aggregate Base, for which a pay item will be added in Addendum No. 2.
Inq. 163Post Date:   11/5/2015Inquiry Date:   10/22/2015
 Q. It appears that Items 4004-400000 S6 Box Culvert-12’zx6' STA 809+70 and Item 4071-440105 Single Reinforced Concrete Box Culvert S6 are both for the construction of S6 Box Culvert. Please confirm that these items are duplicated.
 A. These items are duplicated. Item 4004 will be removed in Addendum No 2.
Inq. 162Post Date:   11/5/2015Inquiry Date:   10/22/2015
 Q. On sheet S13-4 Note 4 states “The cost of undercutting below the footing and backfill to the bottom of footing shall be measured and paid for as separate cubic yard pay Items.....'' Please provide these pay items. Also, please specify the backfill material required.
 A. The pay items will be added in Addendum No. 2
Inq. 161Post Date:   11/5/2015Inquiry Date:   10/22/2015
 Q. Please clarify the difference in scope covered under pay Item 4004 "S6 box culvert -12'x6' Sta 809+07" and Item 4071 "Single Reinforced Concrete Box Culvert S6".
 A. These two pay items are redundant. Item 4004 will be removed. Item 4067 for Category Code No. 440105 will remain.
Inq. 160Post Date:   11/5/2015Inquiry Date:   10/22/2015
 Q. Please clarify where the 13 foot undercut excavation and backfill under .the box culvert as per note 3 on sheet S6·4 gets paid?
 A. The amount of overexcavation has been reduced significantly. The revised extent of overexcavation, along with how this work is to be paid, is shown in the Addendum 2 plans.
Inq. 159Post Date:   11/5/2015Inquiry Date:   10/21/2015
 Q. The cross sections and roadway plans show retaining wall S3 starting at I-270 sta. 286+10.70 and continuing to Bridge S4 wing wall II. The plans provided for retaining wall S3 show the wall starting at I-270 sta. 281+42+/·.The cross section for I-270 SB Off Ramp coincide with the structure plans provided. Please clarify.
 A. The roadway plans will be corrected to match the structure S3 plans.
Inq. 158Post Date:   11/5/2015Inquiry Date:   10/19/2015
 Q. Please clarify under which pay items do the 48” water and 12" sanitary pipe runs get paid? There is no pay item for the pipe runs,
 A. Addendum 1 will address this comment.
Inq. 157Post Date:   11/5/2015Inquiry Date:   10/19/2015
 Q. There are no profiles for the existing or the relocated water/sewer lines. Please provide the profiles to determine the pipe depths and any utility crossings in the way of work
 A. Addendum 1 will address this comment.
Inq. 156Post Date:   11/5/2015Inquiry Date:   10/19/2015
 Q. Per the erosion and sediment control drawing EP-001, the new water and sewer lines will be jacked and bored In locations outside of LOD and a stretch of the pipe Is shown as jacked and bored. But the utility relocation drawings UT-03 and partly UT-09 for the same stretch of pipe does not show any indication of jack and bore pipe run. Please provide the stretch of pipes getting jacked and bored, Also, there is no separate pay item for the jack and boring of the relocated water and sewer line, please add.
 A. All water and sewer facilities to be installed via open cut.
Inq. 155Post Date:   11/5/2015Inquiry Date:   10/16/2015
 Q. The typical sections of retaining wall 14 does not indicate the type of concrete for the footing, wall, coping and parapet. Please provide this information.
 A. As noted in the General Notes, concrete for cast-in-place wall shall be Mix No. 3 (3500 psi). Concrete for parapet and moment slab shall be Mix No. 6 (4,500 psi). Concrete for precast MSE wall panels shall be Mix No. 6, except that the design compressive strength shall be 5,000 psi. Concrete for unreinforced leveling pad shall be Mix No. 1 (2,500 psi). All other concrete shall be Mix No. 3 (3,500 psi).
Inq. 154Post Date:   11/5/2015Inquiry Date:   10/19/2015
 Q. The typical sections for the retaining wall 14 show chain link fence type 3 for some sections however the fence is not shown on the wall elevation drawings 514-2 through 514-7 to determine the exact limits of the fence. Please provide the missing information so that the fence length can be determined.
 A. Addendum No. 1 addresses this issue. The chain link fence has been added to the elevation views as well as all typical sections.
Inq. 153Post Date:   11/5/2015Inquiry Date:   10/16/2015
 Q. Are Bid Items No. 8068 and 8069 duplicate bid items?
 A. Yes, they will be combined in Addendum 2.
Inq. 152Post Date:   11/5/2015Inquiry Date:   10/16/2015
 Q. Are Bid Items No. 8025 and 8026 duplicate bid items?
 A. Yes, they will be combined in Addendum 2.
Inq. 151Post Date:   11/5/2015Inquiry Date:   10/16/2015
 Q. Are Bid Items No. 8021 and 8022 duplicate bid items?
 A. Yes, they will be combined in Addendum 2.
Inq. 150Post Date:   11/5/2015Inquiry Date:   10/16/2015
 Q. The roadway plans (see drawings PS-02 through PS-04) indicates Retaining Wall S2 starting at Station 272+37 and ending at Station 283+46 B/L Construction I-270. The structure plans (see drawings S2-1 through S2-2) ) indicates Retaining Wall S2 starting at Station 278+45 and ending at Station 283+13 B/L Construction I-270. The project cross sections (see drawings SC-22 through CS-35) also indicates Retaining Wall S2 starting at Station 278+45 and ending at Station 283+13 B/L Construction 1-270. Are the structure drawings correct? If the structure drawings are correct what supports the slope excavation for the widening of l-270 NB from Station 272+37 to 278+45?
 A. The stationing for Structure S2 is correct. Concrete F-Shape barrier will be placed between the Stations 272+37 and 278+45.
Inq. 149Post Date:   11/5/2015Inquiry Date:   10/15/2015
 Q. Per the bid pricing sheet, there is 1074 LF of test piles for HP14x89 plies. However, per the drawing sheet 558 there are no test piles for HP14x89 for structure S14. Please clarify.
 A. Item 4036 of the Schedule of Prices provides a line item for payment for 1,074 LF of HP 14 X 89 bearing piles for S14. Item 4043 provides a line item for payment for 50 LF of HP 14 X 89 bearing test piles for S4. This is the incorrect structure number; it should be S14. Addendum No. 1 provides a test pile location.
Inq. 148Post Date:   11/5/2015Inquiry Date:   10/15/2015
 Q. The 3 feet wide and 4 feet wide soil stabilization matting shown on sheet S12-48 does not clarify the type of matting. Based on the pricing sheet, there are two types of stabilization mattings: Type A and Type E. Please clarify the type.
 A. Soil stabilization matting shall be Type A.
Inq. 147Post Date:   11/5/2015Inquiry Date:   10/14/2015
 Q. Please clarify all concrete staining requirements for this project. Currently appears that Ashlar Stone Architectural Finish receive a "multi-color" stain. Please confirm that no stain is required on any other surface.
 A. Addendum No. 1 or 2 removes the stain requirements for these structures
Inq. 146Post Date:   11/5/2015Inquiry Date:   10/14/2015
 Q. Retaining Wall S14 has standards attached for conduits. The typical section for the wall do not show conduit in the barrier. Please confirm that 2 runs of 3" diameter conduit are required.
 A. Conduit are not required for Retaining Wall S14.
Inq. 145Post Date:   11/5/2015Inquiry Date:   10/13/2015
 Q. Please clarify the color stain requirements at MSE walls S1, S2 & S8. What color is coping and slip panels to receive?
 A. The MSE walls, coping and slip panels do not receive any stain. Addendum No. 1 will answer this question.
Inq. 144Post Date:   11/5/2015Inquiry Date:   10/13/2015
 Q. Please provide the thickness required for the Traffic Signal Support Bracket on Sheet S12-82.
 A. Additional information for the Traffic Signal Equipment Support Bracket will be provided in the near future.
Inq. 143Post Date:   11/5/2015Inquiry Date:   10/13/2015
 Q. Please provide detail on sheets S12-84 and S12-85, these sheet are blank.
 A. Addendum No. 1 provides additional information for these sheets. Additional information will be provided in the near future.
Inq. 142Post Date:   11/5/2015Inquiry Date:   10/13/2015
 Q. Please provide top of abutment stem elevations on sheet S12-14 for abutment Bat girders 7 through 13.
 A. This information will be provided in the near future.
Inq. 141Post Date:   11/5/2015Inquiry Date:   10/13/2015
 Q. The provided length of the piles in the proposal sheet for the bridge structure S-12 is approx. 50% of the pile length calculated based on the provided data of tip and top elevation for the abutments/ wing walls and the four piers, Please revise.
 A. The quantities for bearing piles for Bridge No. 15200, S12, are Item 4033 and Item 4041. Addendum No. 1 revises pile quantities, pile types, and the estimated pile tip elevations.
Inq. 140Post Date:   11/5/2015Inquiry Date:   10/13/2015
 Q. Please confirm that the piles at the wing walls for structure S12 with stepped footings are longer i.e. their tip elevation is still the same as that of the abutment piles.
 A. The wing walls have the same estimated pile tip elevations as the abutments proper.
Inq. 139Post Date:   11/2/2015Inquiry Date:   10/27/2015
 Q. The water/sewer relocation plans are incomplete and provide no details. It is impossible to bid this work without the WSSC Plans. Do you have the WSSC Plans?
 A. Addendum 1 provides additional information for the water/sewer related work.
Inq. 138Post Date:   11/2/2015Inquiry Date:   10/27/2015
 Q. On sheet # 299 of 722 please specify the type of expansion bearing at ABUTMENT B?
 A. The expansion bearing type for Abutment B will be detailed in a future addendum
Inq. 137Post Date:   11/2/2015Inquiry Date:   10/26/2015
 Q. It appears that the water and sewer plans that have been included in the Contract Documents are incomplete and not of sufficient detail to estimate the costs for this work. Please provide complete water and sewer drawings and Special Provisions at your earliest convenience so that this work can be priced.
 A. Addendum 1 will address this comment
Inq. 136Post Date:   11/2/2015Inquiry Date:   10/26/2015
 Q. Item 3011- MEASUREMENT AND PAYMENT. Measurement and payment of the Toe Wood Structure for stream bank protection and habitat creation will be made by the unit contract price per Linear Foot of Toe Wood Installed. The pay item is by the "EACH". How is this to be paid?
 A. Addendum No. 1 addresses this by revising the specification to EACH.
Inq. 135Post Date:   11/2/2015Inquiry Date:   10/26/2015
 Q. MIX 2 CONCRETE FOR MISCELLANEOUS STRUCTURES doesn't show on the plans. What is this item to be used for?
 A. This is the concrete collar for reinforce concrete pipe extensions. Please see Addendum No.1 DWG. NO. DD-05, sheet 95 and DWG. NO. PS-11, sheet 36.
Inq. 134Post Date:   11/2/2015Inquiry Date:   10/26/2015
 Q. Sheet SW-07 shows BS-11C being 321' long. The stationing for BS-11C shows it being 468' long. All the associated quantities, #57, #7, sand, BSM, 6" Underdrain, Class II Excavation imply the shorter length. What is the correct length of the Bio-swale and what are the correct quantities of the associated items?
 A. The length of BS-11C will be 476 FT. All the associated quantities, #57, #7 sand, BSM, 6" Underdrain, Class II Excavation have been revised in Addendum No.1 on DWG. NO. SW-07, Sheet 103.
Inq. 133Post Date:   11/2/2015Inquiry Date:   10/26/2015
 Q. You show 32 cy of Mix 3 Concrete for Miscellaneous Structures on SW-16 for Concrete Cradle. Bid item 3032 only has 23 cy's. Which quantity is correct?
 A. The quantity will be update in Addendum No.2. The quantity for Mix 3 Concrete will increased from 23 CY to 66 CY.
Inq. 132Post Date:   11/2/2015Inquiry Date:   10/26/2015
 Q. You show 34 cy of Mix 3 Concrete for Miscellaneous Structures on SW-16 for Riser R 6-1. What is this concrete for?
 A. The concrete is for the riser. The riser will be measured and paid for at the contract unit price per cubic yard of Mix 3 Concrete. See Spec 305 Miscellaneous structures, Addendum No.1.
Inq. 131Post Date:   11/2/2015Inquiry Date:   10/26/2015
 Q. There is a detail for a "reverse slope pipe & pond drain detail'' on sheet SW-20. How is this work to be paid?
 A. The reverse slope pipe and the pond drain will be paid under Stormwater Management Risers. See Spec 305 Miscellaneous structures.
Inq. 130Post Date:   11/2/2015Inquiry Date:   10/26/2015
 Q. Sheet SW-16 shows the outfall pipe from the SWM pond as 36" RCP, Roadway plan sheet PS~6 & SW-17 show the pipe as 42''. Which is correct?
 A. The pipe segment from R 6-1 to EW 6-1 is 42” RCP. The pipe size is revised in Addendum No.2 on DWG. NO. SW-16, Sheet 112.
Inq. 129Post Date:   11/2/2015Inquiry Date:   10/26/2015
 Q. Toe Wood Structure specification says Measurement and payment of the Toe Wood Structure for stream bank protection and habitat creation will be made by the unit contract price per Linear Foot of Toe Wood installed. The bid item is by the EACH. Please advise
 A. Addendum No. 1 addresses this by revising the specification to EACH.
Inq. 128Post Date:   11/2/2015Inquiry Date:   10/26/2015
 Q. S4-18 shows beam seat elevations from Elev. 352.55 to Elev. 352.96 and the top of pier cap elevation at elev. 344.55. This is a beam seat height of 8.26'. Please clarify.
 A. The top of pier cap elevation for Bridge S4 is 351.85.
Inq. 127Post Date:   11/2/2015Inquiry Date:   10/26/2015
 Q. Sheets S14-9 & S14-10 note that "proposed sheeting by others to remain". Sheets S14-11 to S14-14 note that 'proposed sheeting to remain in place, cost of sheeting design and construction is incidental to retaining wall. Please confirm that sheeting design and installation ls part of this contract.
 A. Addendum No. 1 addresses this issue. The cost for this sheeting is incidental to Item 4076, Retaining Wall S14.
Inq. 126Post Date:   11/2/2015Inquiry Date:   10/23/2015
 Q. In reference to the Grading Table on plan sheet GT-01, the table indicates that there is no topsoil in any of the cut sections from the cross sections and yet does include 6" of topsoil in the fill sections. If there is 6" of topsoil in the fill sections shouldn't there also be 6" of topsoil in the cut sections? Can the State please revise the Grading Table to account for topsoil in the cut sections?
 A. Topsoil within cut sections was accounted for as Class 1 or Class 2 excavation.
Inq. 125Post Date:   11/2/2015Inquiry Date:   10/23/2015
 Q. In reference to Bridge Structure S4, plan sheet S4-23, can you please provide information on the layout of the cross frames for the bridge?
 A. Addendum No. 1 will address this comment.
Inq. 124Post Date:   11/2/2015Inquiry Date:   10/23/2015
 Q. In reference to Bridge Structure S4, plan sheet S4-43, can you please indicate on the bearing tables the selections that are to be used for the abutments and pier bearings?
 A. The bearing types will be specified on the Framing Plan, Girder Elevations and in the bridge standards.
Inq. 123Post Date:   11/2/2015Inquiry Date:   10/23/2015
 Q. 1.      In reference to Bridge Structure S12, plan sheet S12-92, can you please indicate on the bearing tables the selections that are to be used for the abutments and pier bearings?
 A. This information is available on Drawings S12-52 and S12-53 along the bottom of the framing plans at each substructure unit.
Inq. 122Post Date:   11/2/2015Inquiry Date:   10/23/2015
 Q. 1.      In reference to Bid Item No. 5009, "GRINDING ASPHALT PAVEMENT 0 INCH TO 1 INCH", Pavement Legend No.10 on plan sheet DT-01 indicates a grinding depth of 2 inches. Will the existing pavement grinding have a maximum depth of 1 inch or 2 inches?
 A. This is addressed in Addendum 1, Item 5009 revised to inches
Inq. 121Post Date:   11/2/2015Inquiry Date:   10/23/2015
 Q. There is no pay item to furnish and install temporary precast concrete traffic barriers. Can a pay item be added for this item of work?
 A. This is addressed in Addendum 2. Item 7010 revised.
Inq. 120Post Date:   11/2/2015Inquiry Date:   10/23/2015
 Q. In reference to Bid Item No. 6002, "MODIFIED TYPE A COMBINATION CURB AND GUTTER 12 INCH GUTTER PAN 8 INCH DEPTH", the pavement details on plan sheet DT-01 calls for a 12" depth gutter pan. Should the description for this item be corrected?
 A. Bid Item No. 6002 should read “Modified Type A Combination Curb and Gutter, 12 inch Gutter Pan 12 inch Depth” This is addressed in Addendum 2.
Inq. 119Post Date:   11/2/2015Inquiry Date:   10/23/2015
 Q. What is the pipe wall thickness required for the 48" DIP water line?
 A. Addendum 1 provides the requested information.
Inq. 118Post Date:   11/2/2015Inquiry Date:   10/23/2015
 Q. Please provide WSSC material specifications for the 48" water line realignment.
 A. Addendum 1 provides the requested information.
Inq. 117Post Date:   11/2/2015Inquiry Date:   10/23/2015
 Q. Please provide profile information for the 48" water line realignment shown on drawings 709 through 721.
 A. Addendum 1 provides the requested information.
Inq. 116Post Date:   11/2/2015Inquiry Date:   10/23/2015
 Q. The Special Provision for Toe Wood Structures under Construction (e) It Indicates that Live Whips are required; please advise how these are paid for.
 A. Addendum No 1 revises this Special Provision.
Inq. 115Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Bid Item 8005 is a Pavement marking item; is this intended to be In the 8000 series of items; please advise
 A. Addendum No 1 addresses this, item deleted.
Inq. 114Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Plans sheet 13 for the geotextlle Inclusion says to refer to SP 200 for Installation. There Is no SP 200 Special Provision.
 A. Addendum No. 1 includes this special provision
Inq. 113Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Item 1030 Is for PRECAST TEMPORARY 32 INCH F SHAPE CONCRETE TRAFFIC BARRIER TERMINAL END, 7500 EACH. There is no item for Precast Temporary 32 inch Traffic Barrier. Should item 1030 actually be traffic barrier by the LF?
 A. The Item 1030, CCS No. 121140 PRECAST TEMPORARY 32 INCH F SHAPE CONCRETE TRAFFIC BARRIER TERMINAL END should read Item 1030, CCS No. 121150 PRECAST TEMPORARY 32 INCH F SHAPE CONCRETE TRAFFIC BARRIER 7500 LF.
Inq. 112Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Is It your Intent to open cut the 30" RCP cross pipe from MH-5-3 to MH 5-2A (Sta 265+50) across 8 lanes of traffic? lf so, how is the pavement replacement and barrier replacement paid?
 A. The 30” RCP from MH-5-3 to MH-5-2A is installed by jack & bore. This is indicated on the roadway plan and profile and an item has been added to the cost estimate in Addendum No. 2.
Inq. 111Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Per the Item description for #4090, only the abutments for bridge S4 receive the epoxy protective coating and not the pier whereas for bridge S12 both piers and abutments receive epoxy protective coatings. Please confirm
 A. For Bridge S4, only the abutments receive the epoxy protective coatings
Inq. 110Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Please confirm that the detail G and H only correspond to the sections shown on sheet 7 for Watkins Mill Road as no reference could be found for that pavement section elsewhere
 A. Details G & H mostly correspond to Watkins Mill Road; however, the last approximate 100’ of tie-in for the SB OFF Ramp to MD 124 to the existing ramp to MD 124 contains curb and gutter in a resurfacing section.
Inq. 109Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Per the reforestation law, of the 32.86 acres of land that will be cleared, 9.55 acres will be replanted on site within 1 year of project completion and 23.31 acres will be planted within the same county/ watershed or else a fine of approx. $143,138.16 will be applied. Please clarify that the reforestation plans included with the contract documents accounts for the reforestation requirements account for any plantations that the contractor is responsible for and as long as the contractor completes the scope defined in those drawings, no fee will be levied.
 A. The contractor is not responsible for off-site reforestation planting or payment of $143,138.16. Contractor shall provide for plantings shown and described on the contract documents and specifications.
Inq. 108Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Drawing S10-1 note 2, general plan and elevation reference retaining wall S8 for the 34 LF run of 60" RCP pipe extension through the retaining wall. Please confirm that it is retaining wall S13 and not S8.
 A. Addendum No. 2 will answer this question.
Inq. 107Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Per the bid proposal sheet there are two types of chain link fences for structure S16 — Item #4095: chain link fence type 2 and #4104: chain link fence type 3. However, per the drawings, there is only type 3 chain link fence. Please clarify.
 A. Addendum No. 1 identifies the limits of Type 2 and Type 3 Chain Link Safety Fence. Type 2 Chain Link Safety Fence is located at the interface with Bridge S12 as the fence transitions down from the height at the bridge (Type 2) to the height of the Type 3 Chain Link Safety Fence which runs down the majority of the wall.
Inq. 106Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. As the proposed ground line is much higher than the existing ground line for wall sections 16A and 16B, please confirm that the extra fill material is included as a part of common borrow pay item # 2006. If not, then please clarify the fill type and where it gets paid.
 A. Addendum No. 1 addresses this. Structure sheets 597-599, 623 and 626 revised.
Inq. 105Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Please confirm that the common borrow between retaining walls S15 and S16 are included in the bid item 2006.
 A. Addendum No. 1 addresses this. Structure sheets 597-599, 623 and 626 revised.
Inq. 104Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Per the special provision in specifications, section 450.04 Measurement "The cast In place concrete traffic barrier in front of retaining wall S2, S8 and S15 will not be measured but the cost will be incidental to the pertinent retaining wall Item." The traffic barrier in front of the retaining wall S8 shown on drawing S8-7 references standard MD 843.53 and the traffic barrier in front of retaining wall S2 shown on drawing S2-6 references standard MD 648.53, please clarify if that barrier will be incidental to the retaining wall.
 A. Addendum No. 1 will address this comment.
Inq. 103Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Per the special provision in specifications, section 450.04 Measurement The cast in place concrete traffic barrier in front of retaining wall S2, S8 and S15 will not be measured but the cost will be incidental to the pertinent retaining wall item." There is no cast in place traffic barrier in front of structure S15, please clarify.
 A. Addendum No. 1 will address this comment.
Inq. 102Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Per the bid proposal sheet there are two types of chain link fences for structure S15 — item #4094: chain link fence type 2 and #4103: chain link fence type 3. However, per the drawings, there is only type 3 chain link fence. Please clarify.
 A. Addendum No. 1 identifies the limits of Type 2 and Type 3 Chain Link Safety Fence. Type 2 Chain Link Safety Fence is located at the interface with Bridge S12 as the fence transitions down from the height at the bridge (Type 2) to the height of the Type 3 Chain Link Safety Fence which runs down the majority of the wall.
Inq. 101Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. The typical MSE wall sections shown on the drawings for structure S15 do not show any geotextile separation between the retaining wall fill and common borrow. Please confirm
 A. Because the design provides for 1’?0” of No. 57 Stone beyond the length of the wall reinforcement straps, no geotextile is required between the stone backfill and the common borrow.
Inq. 100Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. The typical MSE wall sections shown on the drawings for structures S15 and S16 do not show any geotextile separation between the retaining wall fills. Please confirm
 A. Due to the fact that the length of the MSE wall reinforcement straps for S15 and S16 will overlap at the north ends of the walls, the MSE retaining backfills are not separate but a single backfill, and no geotextile is required. Additionally, where the reinforcement straps for the walls do not overlap, the geotextile is not required.
Inq. 99Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Per note 1 on sheet 568, It states that the "precast parapet and moment slab will not be permitted". Please clarify why precast parapet and moment slab cannot be used?
 A. MSHA requires cast-in-place concrete for these elements.
Inq. 98Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. There is no typical detail for wall section 14H for retaining wall S14.
 A. Addendum No. 1 corrects the labeling of the retaining wall typical sections.
Inq. 97Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Please provide details of the expansion joint for the retaining wall S14 at the MSE wall panels without concrete curtain wall i.e. for wall type 14F and 14G.
 A. Addendum No. 1 provides additional details for Retaining Wall S14.
Inq. 96Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Please provide details of the expansion joint for the retaining wall S14 at the MSE wall panels with concrete curtain wall i.e. for wall type 14E.
 A. Addendum No. 1 provides additional details for Retaining Wall S14.
Inq. 95Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Sheet #555, drawing S14-7 states the elevation of top of concrete coping for wall section 14H at the end of RW as 378.64 however, It should be lesser than the top of previous section which is 368.04, Please provide the revised elevation of the end of the RW edge.
 A. The correct elevation for the end of Retaining Wall S14 is El. 358.64.
Inq. 94Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Please provide water level for borings along retaining wall S1 shown on drawing S1-11
 A. Water was not observed at the time of the readings in any of the S1 borings. However, the borings caved/collapsed at depths ranging from 19 to 35.3 feet below ground surface. This cave depth, particularly in granular soils, can be an indication of groundwater level.
Inq. 93Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. The specifications special provisions include section 440 — pre-stressed concrete beams and slab panels. The drawings do not show any structure with pre-stressed concrete beams, please confirm that the project does not have any pre-stressed concrete beams or identify the structure that has pre-stressed concrete beams and slabs.
 A. There are no prestressed structures on this project.
Inq. 92Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Per note 4 on sheet 538, the class 3 excavation for structure S13 shall be paid as a cubic yard item and not in the LS item. However the proposal sheet does not have a separate line for class 3 excavation for structure S13 so please add a separate pay item for it.
 A. Addendum No. 1 will address this comment.
Inq. 91Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Please provide the bearings types for bridge 54 including abutment B of the bridge.
 A. Addendum No. 1 will address this comment.
Inq. 90Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Please confirm that the benched portion in front and at back of the MSE wall for structure S14 next to the reinforced strip area can be backfilled with the excavated material. The typical sections on sheets 563 through 566 show that area within the limit of excavation incidental to the retaining wall but no fill type is indicated. Please clarify
 A. If the excavated material meets the requirement of Common Borrow, it may be used as backfill behind the MSE retaining wall No. 57 Stone backfill.
Inq. 89Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. The MSE walls S2 and S8 show select borrow in the typical section for the sloped section next to the MSE reinforcing strip area. However, MSE wall S1 on sheet S1-4 labels that as excavation. Please confirm that the backfill for structure 1 in that section will be with select fill material only.
 A. The backfill for MSE wall S1 will be identified as select backfill. Select backfill will not be measured but the cost will be incidental to the pertinent retaining wall item.
Inq. 88Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. There is a pay item for select borrow, pay item 2005 with a quantity of 700 cy. The MSE wall drawings also show select borrow fill in the slope area. Please clarify where MSE select fill gets paid?
 A. Select backfill for MSE walls will not be measured but the cost will be incidental to the pertinent retaining wall item.
Inq. 87Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Sheet 389 shows the pay limit for structure S8's class 3 excavation (pay item 4016) and select fill. Please clarify where the select fill for the structure gets paid?
 A. Addendum No. 1 will address this comment.
Inq. 86Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Type K traffic barrier end treatment, any option is paid under bid items 6017 and 6018. Please clarify why the two items are separated when the bid item description is the same?
 A. Items were separated as 6 of the end treatments are on Roadway Plan sheets and 2 are on the Signing sheets outside of the Roadway plan sheet area. For clarity, they will be combined to item 6017 in Addendum No. 2
Inq. 85Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Please clarify where the 965 LF of grass swales shown on the storm water management drawings get paid?
 A. See Addendum No. 1. Quantities for the 529-ft and 436-ft grass swales (total length of 965 LF) are displayed on SW-03 and SW-05, respectively. The quantities for these are included in the pay items for Type A Matting and Turfgrass Establishment.
Inq. 84Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Please provide the detailed specification and pipe class for the PVC sewer line,
 A. Addendum 1 will address this comment.
Inq. 83Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. The drawings show 12" sewer line and there is a pay Item (Item #8043) for 15" PVC sewer line. Please clarify if that is meant to be 12" PVC line?
 A. Addendum 1 will address this comment.
Inq. 82Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Please provide required details for the 12" sewer line, 30" RCP storm line and 48" water line that gets jack and bored.
 A. A detail will be provided for the 30” RCP jack and bore at a later time. All water and sewer facilities to be installed by open cut.
Inq. 81Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Please provide a separate pay item for the pipe run that gets jack and bored.
 A. A separate pay item has been added for the jack & bore in Addendum No. 2 cost estimate.
Inq. 80Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. The 30" RCP utility line from MH 5-3 to MH 5-2A goes across the existing 1-270 however, the neither the drainage profile on drawing DP-04 or the roadway plan drawings show the pipes to be jack and bored. The erosion and sediment control drawing EP-204 however shows jacking and boring. Please indicate the pipe sections that get jack and bored in the roadway plan and drainage profile drawings as well.
 A. The proposed jack and bore 30” RCP from MH-5-3 to MH-5-2A has been indicated on the roadway plan and profile in Addendum No. 2.
Inq. 79Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Item 1030 – 7500 ‘EA’ of “Precast Temporary 32 Inch F Shape Concrete Traffic Barrier End Treatment”. Please clarify that the unit and description are correct.
 A. Addendum No. 1 will address this comment.
Inq. 78Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. 1.      Water/Sewer Relocation Plan shows 30 proposed sanitary manholes. The only bid item for them is No. 8042 812250, 200 lf of Precast Sewer Manhole (48 Inch)-Vertical Depth. Please clarify where the minimum depth manhole boxes should be priced.
 A. Please review the WSSC Standard Details and Standard Specifications regarding sanitary sewer manholes. These WSSC documents are available online, the website is provided in the Addendum 1 documents.
Inq. 77Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. Please provide a specification for the cellular confinement load support system required in Item 3112.
 A. Addendum No. 1 provides this specification for Access Road with Cellular Confinement Load Support System.
Inq. 76Post Date:   11/2/2015Inquiry Date:   10/22/2015
 Q. There are several drawings that are incomplete for the design of Structure S-4. Could you please provide complete drawings for contractors to price?
 A. Addendum No. 1 will address this comment.
Inq. 75Post Date:   11/2/2015Inquiry Date:   10/21/2015
 Q. Sheet S5-11 through S5-13 show porous backfill behind the wall at a 2' wide on top of the drain block sloping up at 1:2. The standard provided on sheet S5-16 required 2 cubic feet of porous backfill at each weep hole. This is also the case with retaining wall S7. Please clarify which is correct.
 A. Addendum No. 1 will address this comment.
Inq. 74Post Date:   11/2/2015Inquiry Date:   10/21/2015
 Q. Please provide As-Built drawing for the existing MSE retaining wall along 1-270 SB at proposed retaining wall S14.
 A. Addendum No. 1 will address this comment.
Inq. 73Post Date:   11/2/2015Inquiry Date:   10/21/2015
 Q. Retaining Wall S1 is shown as a MSE wall. The right-of way at I-270 NB on Ramp sta. 205+40+/­ does not allow room for MSE straps. Also, this wall appears to be shown as a soldier pile and lagging wall on the cross sections sheet 50 of 153. Please clarify.
 A. Retaining Wall S1 is a MSE wall. The straps do extend beyond the ROW, but there is a perpetual easement behind the ROW line, where the straps will lie within.
Inq. 72Post Date:   11/2/2015Inquiry Date:   10/21/2015
 Q. There are 2 existing MSE walls on I-270 Northbound. One from sta. 255+00+/- to sta. 261+50+/·, another from sta. 264+50+/- to 167+00+/-. According to the cross section these wall need to be removed. Removal Bid Items have not been provided. How will the removal be paid? Also please provide as-built plans for these two walls?
 A. Addendum No. 1 will address this comment.
Inq. 71Post Date:   11/2/2015Inquiry Date:   10/20/2015
 Q. Drainage Structure Schedules on sheet DD-01 shows (17) PRECAST MODIFIED TYPE S COMBINATION INLET DOUBLE GRATE TANDEM, which corresponds to item 3007 300000_ Drainage Structure Schedules does not show any STANDARD TYPE S INLET. Could you please clarify where the (15) EA of STANDARD TYPE S INLET DOUBLE GRATE TANDEM under item NO. 3065 379120 will be used?
 A. See Addendum No. 1. There are now (18) PRECAST MODIFIED TYPE S COMBINATION INLET DOUBLE GRATE TANDEM in the Structure Schedule and the “(15) EA of STANDARD TYPE S INLET DOUBLE GRATE TANDEM” has been removed in the cost estimate.
Inq. 70Post Date:   11/2/2015Inquiry Date:   10/20/2015
 Q. Item NO. 3042 304124, 252 If of 24 INCH CORRUGATED STEEL PIPE, and item NO. 3046 340024, 581 If of 24 INCH CORRUGATED POLYETHYLENE PIPE, cannot be found on Drainage Schedules, Drainage Profiles, or Roadway Plan. Could you please clarify their location?
 A. The CSP and PEP quantities have been revised. Please see the Erosion and Sediment Control plans for the quantity schedules.
Inq. 69Post Date:   11/2/2015Inquiry Date:   10/19/2015
 Q. On plan sheet S2-6, Structure S2, the MSE panel wall shows excavation to be as steep as ground will allow to the ROW line. Is this meant to be the Ex. ROW? If the ROW is supposed to be the Ex ROW shown on plan sheet 191 from sta 278+00 thru 283+00 Rd then this is not enough room to excavate the wall to the ROW line. Shoring will be required if there is no more ROW. Would you establish a SF item for temporary shoring?
 A. The top of cut for the MSE wall does not have to be within the ROW. There is a construction easement beyond the ROW line. The use of shoring is not anticipated.
Inq. 68Post Date:   11/2/2015Inquiry Date:   10/19/2015
 Q. There is no pay item for 18'' CMP pipe run shown on sheet DP-01 between MH/2-9 and Ex-1/2-3. Please clarify where the CMP pipe will be paid?
 A. Pipe from MH-2-9 to EX-I-2-3 is proposed 18” RCP.
Inq. 67Post Date:   11/2/2015Inquiry Date:   10/19/2015
 Q. Drawing PS-02 shows 18" ECP line between MH/2·9 and Ex-1/2-3 whereas drawing DP-01 shows that run to be 18" CMP pipe. Please clarify
 A. See Addendum No. 1. PS-02 and DP-01 show proposed 18” RCP running from MH-2-9 to EX-I-2-3.
Inq. 66Post Date:   11/2/2015Inquiry Date:   10/16/2015
 Q. Are Bid Items No. 6017 and 6018 duplicate bid items?
 A. Yes, they will be combined in Addendum 2.
Inq. 65Post Date:   11/2/2015Inquiry Date:   10/16/2015
 Q. Bid Item No. 1030, PRECAST TEMPORARY 32 INCH F SHAPE CONCRETE TRAFFIC BARRIER TERMINAL END, has a bid quantity of 7,500 each. These terminal ends don't appear to be called for anywhere in the maintenance of traffic plans. Can the State provide direction as to where these terminal ends are used?
 A. Item No. 1030 should read CCS Number 121150, 7500 LF of PRECAST TEMPORARY 32 INCH F SHAPE CONCRETE TRAFFIC BARRIER and not as CCS 121140 PRECAST TEMPORARY 32 INCH F SHAPE CONCRETE TRAFFIC BARRIER TERMINAL END This will be included in Addendum 2
Inq. 64Post Date:   11/2/2015Inquiry Date:   10/16/2015
 Q. Retaining Wall S1 adjacent to the 1-270 NB on Ramp runs from Station 204+00 to 206+00 (see structural drawing S1-l). This wall does not show up on the cross sections (see drawings CS-8 through CS-12). Can the cross sections be corrected to include this retaining wall?
 A. Addendum No. 1 addresses this issue. The cost for this sheeting is incidental to Item 4076, Retaining Wall S14.
Inq. 63Post Date:   11/2/2015Inquiry Date:   10/16/2015
 Q. The water/sewer relocation plan (see drawings UT-01 through UT-13) do not provide sufficient information to price these relocations. Can the State provide profiles for these relocations that includes information on pipe, fittings and existing utilities?
 A. Addendum No. 1 has updated all Utility Plans
Inq. 62Post Date:   11/2/2015Inquiry Date:   10/16/2015
 Q. The drainage profile for MH/5-3 to MH/5-2A (see drawing DP-04) indicates that the 30" RCP is to be installed using an open cut trench across NB & SB I-270. Is this correct or should this pipe be jack & bore?
 A. Addendum No. 1 has updated Roadway Plan PS-04 and Drainage Profile DP-04. The pipe will be jack and bore.
Inq. 61Post Date:   11/2/2015Inquiry Date:   10/16/2015
 Q. Plans sheets Sl2-9, S12-20 S12-84 and S12-85 have title box indicting plan type information, but are blank of all other information. Can these plans be connected and reissued?
 A. Addendum No. 1 has updated Structure 12
Inq. 60Post Date:   11/2/2015Inquiry Date:   10/16/2015
 Q. Plan sheets S4-5 through S4-17, S4-26, and S4-31 through S4-34 appear to be missing information that is needed to determine cost. Please confirm that these plan sheet will be corrected and made available to all plan holders.
 A. Addendum No. 1 will have more complete drawings for Structure S4.
Inq. 59Post Date:   11/2/2015Inquiry Date:   10/16/2015
 Q. The Index of Sheets, Sheet No. 2 of 722, Culvert Plans and Profiles sheets 88 of 722 and 89 of722. There is an additional Culvert plan, sheet 90 of722 that is not indicated on the Index of Sheets, please clarify?
 A. Addendum No. 1 has corrected the Index of Sheets
Inq. 58Post Date:   11/2/2015Inquiry Date:   10/16/2015
 Q. The Index of Sheets, Sheet No. 2 of 722 indicates that there are 452 plan sheets. There are 722 plans sheets. Can the Index of Sheets be corrected and made available to all plan holders?
 A. Addendum No. 1 has corrected the Index of Sheets
Inq. 57Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. For retaining wall S14, please clarify if the cost of the sheet piles along the MSE wall side will be a part of this contract or another? Drawings S14-9 and S14-10, state proposed sheeting "by others" to remain' which implies that the sheeting will be a part of another contract. However, the typical section drawings S14-12, S14-13 and S14-14 has a note pointing to the sheet pile stating 'proposed sheeting to remain in place, cost of sheeting design and construction is "incidental" to the retaining wall'. Please clarify scope coverage.
 A. Addendum No. 1 addresses this issue. The cost for this sheeting is incidental to Item 4076, Retaining Wall S14.
Inq. 56Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. Per the bid price sheet, there is no line item for the production piles HP14x89 for retaining wall S14. Please add the line item for it
 A. Item 4036 of the Schedule of Prices provides a line item for payment for 1,074 LF of HP 14 X 89 bearing piles for S14.
Inq. 55Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. The typical sections for the retaining walls show chain link fence type 3 however the fence is not shown on the wall elevation drawings S5-3 through S5-4 to determine the limits of the fence. Please provide the missing information so that the fence length can be determined.
 A. Addendum No. 1 will address this comment.
Inq. 54Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. Phase provide the bottom of footing for the retaining wall 5, wall section C-C shown on sheet S5-4 so that the wall height can be calculated.
 A. Addendum No. 1 will address this comment.
Inq. 53Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. Please correct the stationing for the retaining wall S5. Drawing S5·3 shows station 808+87.48 at the start of culvert S6 and the same stationing is shown for the wall on drawing S5-4 in the wall portion that falls under wall section BB.
 A. Addendum No. 2 will address this comment.
Inq. 52Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. There is a separate pay Item for concrete footing for retaining wall S15 whereas no separate pay Item is included for the concrete footing for any other retaining wall structure. Please confirm that for all other retaining walls, the footing is included with the retaining wall pay item.
 A. The pay items provided in the Schedule of Prices are consistent with the plan details and notes.
Inq. 51Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. Please provide information on the type of fixed and expansion bearing for both bridge structures S4 and S12.
 A. Addendum No. 1 will address this comment. The types of fixed and expansion bearings for S12 may be found on Drawings S12-52 and S12-53 along the bottoms of the plans at each substructure unit.
Inq. 50Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. Sheet S12-64 note 1 references framing plan drawing for location of the traffic signal support. The framing plan sheets S12-52 and S12-53 however does not indicate the location of the traffic signal supports however 1 traffic signal support is shown on the deck slab pour sequence drawing S12-66. Please revise the framing plan to reflect the location of the signal support and confirm that only 1 ea signal support will be needed for bridge S12.
 A. The location for the Traffic Signal Support Bracket shown on Drawing No. S12-63 is shown on the Framing Plan on Drawing S12-53. It appears on the south side of the bridge a few feet to the right of Field Splice 4 in Addendum No. 1. There is a note, “Additional Intermediate Cross Frame at Traffic Signal Support Bracket (Typ.)”. The item appearing on the Drawing No. S12-66 is the Traffic Sign Equipment Support Bracket, which is shown on Drawing No. S12-82. There is only one of each of these items. However, there is a reinforced concrete Median Traffic Signal Pole Support Base shown on Drawings S12-84 of Addendum No. 1. Future plan revisions will provide additional information on all three of these features.
Inq. 49Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. Bid item 4101 in the price sheet is a lump sum item for Chain Link Fence Type 3 for structure S12. However, per the drawings there are only type 1and type 2 chain link fences on the bridge, Please clarify.
 A. Type III Chain Link Safety Fence is to be placed around the perimeter of the Traffic Signal Equipment Support Bracket, shown on Drawing S12-82. Redline Revision No. 1 will provide additional information.
Inq. 48Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. Per sheet 427, abutment A: the stern is shown as 5'2" whereas the beam seat is 3'6" and the back wall is shown as 1feet, which adds up to 4'6". Additionally, section A on S12-4 drawing shows the width as 4'6". Please revise the abutment stem width to make it consistent.
 A. The 4’ 6” abutment stem width is correct. Addendum No. 1 corrects this dimension.
Inq. 47Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. Please clarify the intent of drawings S4-34 through S4-36. The bridge S4 along ramp 8 is a new bridge so please clarify why the bridge deck will need to be demolished and then reconstructed in two sections as shown on S4-34 to S4-36 drawings. The MOT plans do not indicate any such need for project construction.
 A. Drawing Nos. S4-34 through S4-36 are for informational purposes only. They will be used for reference if and when the concrete deck is replaced in the future.
Inq. 46Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. The provided details for the bridge structure S4 are insufficient to do the quantity take-off for the structure. Please add relevant information to allow detailed take-off of the structure.
 A. Addendum No. 1 will address this comment.
Inq. 45Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. There are blank pages included in the drawing set, for ex. Sheets 433, 444, 508, 509 -please confirm that these were meant to blank pages.
 A. Addendum No. 1 will have more complete drawings for Structure S12.
Inq. 44Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. Sheet S4-26 seems to be incomplete. It calls out the camber but no information is provided.
 A. Addendum No. 1 will address this comment.
Inq. 43Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. The cross frames details for bridge structure S4 on drawings S4-29 and S4-30 only labels one of the diagonal angles. Please confirm that all three angles of the cross frame are L4x4x3/8 including the bottom chord.
 A. All angles for the cross frames are to be 4x4x3/8.
Inq. 42Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. The elevation drawings for abutments at structure S4 do not provide any levels or details. Please revise.
 A. Addendum No. 1 will address this comment.
Inq. 41Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. The reinforcing drawings in typical sections of the abutments and wingwalls at bridge S4, sheets: S4-9, S4-14, S4-16, S4-17 do not label the rebars. Please correct.
 A. Addendum No. 1 will address this comment.
Inq. 40Post Date:   11/2/2015Inquiry Date:   10/15/2015
 Q. The reinforcing drawings for Bridge S4: sheets S4·7, S4-8, S4·12, S4-13 do not show any reinforcement bars. Please revise.
 A. Addendum No. 1 will address this comment.
Inq. 39Post Date:   11/2/2015Inquiry Date:   10/14/2015
 Q. Please provide Type Ill Chain Link Fence Detail on elevation views for retaining wall S14 including post spacing requirements.
 A. Addendum No. 1 provides the requested details.
Inq. 38Post Date:   11/2/2015Inquiry Date:   10/14/2015
 Q. Sheets S14-12 through S14-16 all have notes stating the concrete barrier cost is incidental to the retaining wall Item. However Item 4062 was provided for “Concrete Parapet Sl4". Please clarify.
 A. The parapet portion of the cast-in-place concrete retaining wall and the moment slab and parapet for the MSE retaining wall for Structure S14 shall be paid under Item 4062, Concrete Parapet S14.
Inq. 37Post Date:   11/2/2015Inquiry Date:   10/14/2015
 Q. Please confirm that all MSE leveling pads are to be 2' wide x 1' thick. Plans for retaining walls S14, S15 & S16 do not call out a dimension.
 A. MSE leveling pads shall be in conformance with the MSE wall manufacturer’s requirements.
Inq. 36Post Date:   11/2/2015Inquiry Date:   10/14/2015
 Q. Sheet S15-6 through S15-8 states that Jersey Shape Traffic Barrier, Type 1, is a separate pay item. However page 127 "Section 450- Retaining Walls" of the special provision states that “The cast in place concrete traffic barrier in front of retaining walls S2, S8 and Sl5 will not be measured but the cost will be incidental to the pertinent retaining wall item. Please clarify which is correct.
 A. Addendum No. 1 will address this comment.
Inq. 35Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. May fence anchor bolts be drilled and grouted?
 A. Fence anchor bolts may be cored and not drilled into the cast-in-place concrete coping. See the pertinent fence standard notes in the drawings.
Inq. 34Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Will precast coping be allowed for retaining walls S1, S2 and S8?
 A. Precast coping will not be allowed for walls S1, S2 and S8.
Inq. 33Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. On MSE walls S15 and S16. Please confirm that if the distance between the pay limits of the Lump Sum walls is less than 8’, backfill will not be paid as Common Borrow but shale be incidental to the Lump sum wall Items. Reference S16-7.
 A. Addendum No. 1 removes the typical section in question. Only No. 57 Stone backfill will be placed between the MSE retaining walls.
Inq. 32Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. On Sheet S16-3 the dimension shown at end of MSE wall of 11-3/8" is incorrect. Should be 8'-11-3/8".
 A. This item will be corrected as noted in the near future.
Inq. 31Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Please provide a detail for the required railing and method of payment for the railing shown in sheet S12-82.
 A. This railing is Type III Chain Link Safety Fence and is paid for by Item 4101.
Inq. 30Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. On Sheet S12-92 please provide required bearings in data schedule.
 A. This information is available on Drawings S12-52 and S12-53 along the bottom of the framing plans at each substructure unit.
Inq. 29Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Sheets S12-9 and S12·20 for the abutment beam seat plans are blank. Please provide the information on these sheets.
 A. Addendum No. 1 provides details for these elements.
Inq. 28Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Can the State please clarify which Type K inlets are single and which are double? The structure schedule does not differentiate.
 A. Addendum No. 1 has added clarification in the Remarks column of the structure schedules.
Inq. 27Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. In regards to Plan Sheet S10-1, Note 7- Will this undercut be paid for under the contract line item (3027) or is this undercut incidental to the pipe?
 A. Addendum No. 1 has additional bid item for the excavation and back fill for the undercut of the pipe.
Inq. 26Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Can the State please confirm the scopes of structures S8 and S10?
 A. Structure S8 includes the retaining wall from limits Station 247+45.63 to Station 252+00. Structure S10 is the end wall at the outfall of the 72” RCP. The pipe, the collar connecting to the existing pipe, the junction box and riser shown on the drawing has separate bid items. Addendum No. 1 specifies several of these items. Addendum No. 2 will clarify the remaining.
Inq. 25Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. The drawings for 58 show the limits of the wall stopping at Sta. 252+00 +/-and the S10 drawings show 58 extending beyond Sta. 254+00. Please confirm the limits of S8.
 A. The label on Drawing S10-1 is incorrect, that should be Wall S-13. This will be corrected in Addendum No. 2.
Inq. 24Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Could the State please provide a detail for HW-6-1? The structure schedule indicates that a detail is shown on DD-06 but one is not present.
 A. In Addendum No. 1, the detail for HW 6-1 has been provided in DWG. NO. S13-07, sheet 546. Structure schedule has been revised to show the correct location of the detail.
Inq. 23Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Can the State please provide a profile for the runs of pipe between I-11-1 and Ex. Pipe and I-11-2 and Ex. Pipe?
 A. In Addendum No. 1, the profiles for those two connections have been added in DWG. NO. DP-06, sheet 85.
Inq. 22Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Can the State please clarify whether the run of storm drain from I-5-10 to I-10-1 is to be 15" or 18"?
 A. The pipe from I-10-5 to I-10-1 is 43 LF 15” RCP.
Inq. 21Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Could the State please clarify the horizontal limits of the undercut on S8?
 A. Addendum No. 2 will show the horizontal limits for the undercut as shown on Drawing S8-7.
Inq. 20Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Could the State please provide a profile for the run of storm drain between MH-9-2 and PP-9-1?
 A. A profile has been added for MH-9-2 to PP-9-1 to sheet 83, drawing DP-04, in Addendum No. 1.
Inq. 19Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Could the State please provide a connection detail for how I-5-SC and I-5-5D and I-5-5A and I-5-5 shall be connected?
 A. A modified S-2 inlet detail has been provided on sheet 96 of 722, drawing DD-06, in Addendum No. 1.
Inq. 18Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. The storm drain schedule lists a proposed run of 24" Class IV RCP between MH-4-2 and MH-4-1. A pipe profile is not provided for this run and the roadway plan does not show a run of proposed pipe at this location. Could the State please provide direction?
 A. The pipe from MH-4-2 to MH-4-1 is an existing pipe and has been removed from the storm drain schedule in Addendum No. 1.
Inq. 17Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. On the set of drawings downloaded from eMaryland Marketplace, it appears that some layers on the original CAD files may be missing (specifically S4 and S5). Could the State please review and advise how we can obtain the complete drawings?
 A. Addendum No. 1 will have more complete drawings for Structures S4 and S5.
Inq. 16Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Sheets S4-29 and S4-30 show intermediate cross frames but there is no plan view showing the location of cross frames or number of cross frames between 2 girders. As the intermediate cross frames have 8"x1/2" connection plates which are not shown on girder elevations, their locations/ number of Intermediate cross frames cannot be determined.
 A. Addendum No. 1 will address this comment.
Inq. 15Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Per the details on sheet S4-27, there are 61'x1/2" and 8"x1/2 stiffener plates but the girder elevations do not show these. Please show their location on girder elevations.
 A. Stiffener plate locations will be shown on the Girder Elevations sheet. Intermediate cross frame connection plates will not be shown on the Girder Elevations sheet. Please refer to the framing plan for connection plate locations.
Inq. 14Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Sheet S4-24 and S4-25 show that the girders for bridge S4 have 8.5" x 5/8'1 bearing stiffener at abutments. However, per the bearing stiffener details on sheet S4-28 and the cross frame detail at abutments on sheet S4-29 and S4-30, the bearing stiffener is 8"x5/8". Please clarify
 A. Addendum No. 1 will address this comment.
Inq. 13Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Please confirm that for bridge S4 only the two abutment footings sit on piles and not the pier footing.
 A. Abutments A and B will be on steel H-piles and the pier will be on a spread foundation.
Inq. 12Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Per the bid proposal sheet for structure S4, there are no production plies but only test piles-1336 LF and 50 LF of HP12 x74 and HP 14x89. However, per the provided bridge S4 drawings, there are only production piles and no test piles. Please revise.
 A. Addendum No. 1 will address this comment.
Inq. 11Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. No details are provided on the S4 structure drawings to determine the pile type but per tl1e bid proposal sheet, there are two piles types for the structure HP12x74 and HP14x89. Please provide the appropriate details.
 A. Addendum No. 1 will address this comment.
Inq. 10Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Although sections are shown for the S4 structure abutments, no elevation has been provided for the bottom of footing to determine top of piles.
 A. Addendum No. 1 will address this comment.
Inq. 9Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. No tip elevations have been provided for the piles at the abutments for bridge structure S4. Please provide appropriate information.
 A. Addendum No. 1 will address this comment.
Inq. 8Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Sheet S4-15 states wing wall elevations but it shows Abutment B in plan form. Please provide the wing wall elevations.
 A. Addendum No. 1 will address this comment.
Inq. 7Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. There is a huge discrepancy in pile lengths for all retaining wall structures. The quantities provided for the piles at the retaining walls are approx. 1/3rd of the quantities determined via the provided top and tip elevations of plies taking the slope into consideration for battered piles.
 A. Will look into this and Addendum No. 2 will have any corrections included for the bid items.
Inq. 6Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Based on the total linear footage provided for structure S3 and number of piles shown on the drawings, please confirm that with 1:4 batter, average length is only 19 LF?
 A. The average length of pile for Structure S3 as indicated is correct.
Inq. 5Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Per the bid proposal sheet, there are no production piles for the bridge structure S4. Please revise.
 A. Addendum No. 1 will address this comment.
Inq. 4Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. There are no test piles shown for structures S5 and S7. However the bid proposal sheet shows 25 LF and 50 LF respectively of test piles for these two structures. Please reflect the location of test piles on the drawings.
 A. Addendum No. 1 will address this comment.
Inq. 3Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. Sheet S5-8 shows WSSC sewer line in the footing plan but the elevation on sheet S5-3 does not show any sewer line. Please show the proposed line in elevation as well.
 A. Addendum No. 1 will address this comment.
Inq. 2Post Date:   11/2/2015Inquiry Date:   10/13/2015
 Q. No estimated tip elevation has been provided for piles at 55 and 57 structures. Please provide the missing information.
 A. Addendum No. 1 will address this comment.
Inq. 1Post Date:   11/2/2015Inquiry Date:   10/12/2015
 Q. Pipe Schedule (sheet 93 of 722 of plan) shows that pipe from I-5-1 to I-5-2 is 18" RCP, pipe from I-5-2 to MH-5-3 is 24'' RCP and pipe from MH-2-9 to EX-I-2-3 is 18" RCP. These pipes are shown to be of a different size/material on Drainage Profiles (sheet 80-87 of 722). Could you please clarify what sizes and materials they are?
 A. The pipe from I-5-1 to I-5-2 is 104 LF 24” RCP, the pipe from I-5-2 to MH-5-3 is 163 LF 30” RCP, and the pipe from MH-2-9 to EX-I-2-3 is 40 LF 18” RCP.
 
 

 